Reference -Joints in Concrete Construction, ACI 224.3R, American Concrete
Institute
Concrete expands and
shrinks with changes in moisture and temperature. The overall tendency is to
shrink and this can cause cracking at an early age. Irregular cracks are unsightly
and difficult to maintain but generally do not affect the integrity of
concrete. Joints are simply pre-planned cracks. Joints in concrete slabs can be
created by forming, tooling, sawing, and placement of joint formers.
Some forms of joints are:
- Contraction joints - are intended to create weakened
planes in the concrete and regulate the location where cracks, resulting
from dimensional changes, will occur.
- Isolation or expansion joints - separate or isolate
slabs from other parts of the structure, such as walls, footings or
columns; and driveways and patios from sidewalks, garage slabs, stairs,
light poles and other points of restraint. They permit independent
vertical and horizontal movement between adjoining parts of the structure
and help minimize cracking when such movements are restrained.
- Construction joints - are surfaces where two successive
placements of concrete meet. They are typically placed at the end of a
day's work but may be required when concrete placement is stopped for longer
than the initial setting time of concrete. In slabs they may be designed
to permit movement and/or to transfer load. The location of construction
joints should be planned. It may be desirable to achieve bond and continue
reinforcement through a construction joint.
Why are
Joints Constructed?
Cracks in concrete
cannot be prevented entirely, but they can be controlled and minimized by
properly designed joints. Concrete cracks because:
- Concrete is weak in tension and, therefore, if its
natural tendency to shrink is restrained, tensile stresses that exceed its
tensile strength can develop, resulting in cracking.
- At early ages, before the concrete dries out, most
cracking is caused by temperature changes or by the slight contraction
that takes place as the concrete sets and hardens. Later, as the concrete
dries, it will shrink further and either additional cracks
may form or preexisting cracks may become wider.
Joints
provide relief from the tensile stresses, are easy to maintain and are less
objectionable than uncontrolled or irregular cracks.
How to Construct Joints
Joints must be carefully
designed and properly constructed if uncontrolled cracking of concrete flatwork
is to be avoided. The following recommended practices should be observed:
- The maximum joint spacing should be 24 to 36 times the
thickness of the slab. For example, in a 4-inch [100 mm] thick slab the
joint spacing should be about 10 feet [3 m]. It is further recommended
that joint spacing be limited to a maximum of 15 feet [4.5 m].
- All panels should be squarely or nearly so. The length
should not exceed 1.5 times the width. Avoid :-shaped
panels.
- For contraction joints, the joint groove should have a
minimum depth of 1/4 the thickness of the slab, but not less than 1 inch
[25 mm]. Timing of jointing operations depends on the method used:
- Preformed plastic or hard
board joint strips are inserted into the concrete surface to the required
depth before finishing.
- Tooled joints must be run
early in the finishing process and rerun later to ensure groove bond has
not occurred.
- Early-entry dry-cut joints are
generally run 1 to 4 hours after completion of finishing, depending on
the concrete's setting characteristics. These joints are typically not as
deep as those obtained by the conventional saw-cut process, but should be
a minimum of 1 inch [25 mm] in depth.
- Conventional saw-cut joints should be run
within 4 to 12 hours after the concrete has been finished.
- Raveling during saw cutting is affected by the strength
of the concrete and aggregate characteristics. If the joint edges ravel
during sawing, it must be delayed. However, if delayed too long, sawing
can become difficult and uncontrolled cracking may occur.
- Use premolded joint filler
such as asphalt-impregnated fiber sheeting, compressible foam strips, or
similar materials for isolation joints to separate slabs from building
walls or footings. At least 2 inches [50 mm] of sand over the top of a
footing will also prevent bond to the footing.
·
To
isolate columns from slabs, form circular or square openings, which will not be filled until after the floor has hardened.
Slab contraction joints should intersect at the openings for columns. If square
openings are used around columns, the square should be turned at 45 degrees so
the contraction joints intersect at the diagonals of the square.
- If the slab contains wire mesh, cut out alternate
wires, or preferably discontinue the mesh, across contraction joints. Note
that the wire mesh will not prevent cracking. Mesh tends to keep the
cracks and joints tightly closed.
- Construction joints key the two edges of the slab
together either to provide transfer of loads or to help prevent curling or
warping of the two adjacent edges. Galvanized metal keys are sometimes
used for interior slabs, however, a beveled 1 by 2 inch [25 by 50 mm]
strip, nailed to bulkheads or form boards, can be used in slabs that are
at least 5 inches [125 mm] thick to form a key which will resist vertical
loads and movements. Keyed joints are not recommended for industrial
floors. Metal dowels should be used in slabs that will carry heavy loads.
Dowels must be carefully lined up and parallel or they may induce
restraint and cause random cracking at the end of the dowel.
- Joints in industrial floors
subject to heavy traffic require special attention to avoid spalling of joint edges. Such joints should be filled
with a material capable of supporting joint edges. Manufacturer's
recommendations and performance records should be checked before use.

- Follow
These Rules for Proper Jointing
- Plan exact location of all joints, including timing of
contraction joint sawing before construction.
- Provide isolation joints between slabs and columns,
walls and footings, and at junctions of driveways with walks, curbs or
other obstructions.
- Provide contraction joints and joint filling materials
as outlined in specifications.